Saturday, August 18, 2012

DiMeo Brothers has completed the concrete curb & gutter on the south side of Bel-Air Drive. The contractor has been approved for an early start time on Saturday, August 18th starting at 7:00 AM. The contractor will begin installing asphalt surface driveways and backfilling of new curb.

It is anticipated that all driveways on the south side of the roadway will be opened Monday morning, August 20th.

Curb preparation and installation work on the north side of Bel-Air and both sides of Clavey Lane will commence on Monday morning, August 20th and weather permitting will be completed by Saturday, August 25th.   Driveway access to these homes will be restored beginning Monday morning, August 27th

All cars parked at residences on the north side of Bel-Air and both sides of Clavey Lane will not have access to driveways after 7:00 AM on Monday morning and should park on Fontana or Pick. No cars should be parked on Bel-Air and Clavey between 7:00 AM and 6:00 PM.  Please plan accordingly. 

Once the concrete curb & gutter is installed, the contractor will begin roadway grading.

The Springman Middle School storm sewer project is completed with the exception of site grading and sod installation.

Thank you for your patience during the concrete curb & gutter work last week and next week.