Friday, August 3, 2012



DiMeo Brothers, Inc. installed water services all last week. All water services are now connected to the new water main.

Next week the contractor will connect the new water main to the existing water main. The water main is anticipated to be shut-off for 4-6 hours two days next week. Residents will be notified 24-hours in advance of any water main shut-downs.

The contractor will also perform removal of existing fire hydrants, water valves, and other items; including site clean-up.

Concrete curb & gutter work is scheduled for August 13th on the south side of the roadway.  Residents will be notified prior to concrete work starting. All driveways on the south side of the roadway will be closed during concrete installation and curing.

The Springman Middle School storm sewer project began last week. This work will continue through next week.

Thank you for your patience in advance for the inconvenience of water main shut-downs and upcoming concrete curb & gutter work.