Friday, June 29, 2012



DiMeo Brothers, Inc. continued to install the new 8-inch PVC water main and fire hydrants. Thank you for your patience during the water shut-down this week.

Next week the contractor will complete the water main installation and begin disinfecting and pressure testing the new water main. The contractor is also anticipated to begin storm sewer work.

Water services are not scheduled to begin until after the July 4th Holiday. Notification will be given prior to shutting the water off to your residence.  

Driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you for your patience.

Happy 4th of July.

Friday, June 15, 2012
















DiMeo Brothers, Inc. has completed the sanitary sewer installation along Bel Air Drive and Clavey Lane, including all sanitary sewer services.

The contractor will begin installing new 8-inch PVC Water Main next week.
 
Driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you for your patience.

Friday, June 8, 2012




DiMeo Brothers, Inc. continued to install sanitary sewer main line and services along Bel-Air Drive.  The contractor has completed the sanitary sewer main line and is continuing to work on sanitary sewer services.

Next week the contractor will continue to install sanitary sewer services along the project.    
 
Driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you for your patience.

Wednesday, June 6, 2012

On June 6, 2012, an emergency shut-down of the water main was conducted due to a water main break within the project limits.

Residents were notified of the shut down following the water main being turned off.

Water service to the area has been restored.

If you have cloudy or rusty water coming out of your faucets, please allow to water to run for a few minutes to allow the water to clear.

If you have any additional issues regarding water quality, please contact the Public Works Department at 847-657-3030.

We apologize for any inconvenience this may have caused you.

Friday, June 1, 2012



DiMeo Brothers, Inc. continued to install sanitary sewer main line and services along Bel-Air Drive.  Due to the shortened holiday week and rain, work was limited on-site.

Next week the contractor will continue to install the sanitary sewer along Bel-Air Drive from east to west.  
 
Driveway access may be restricted, but will be restored to residences as soon as possible and at the end of each day. Thank you for your patience.