Friday, August 31, 2012















DiMeo Brothers has completed roadway base work and has installed the first layer of asphalt paving on Bel-Air Drive.  

Next week the contractor will begin cleaning up the site and prepping for restoration.

Vehicles are not allowed to be parked along the Bel-Air and Clavey from 7:00 AM to 6:00 PM throughout the week.

Thank you for your patience during the pavement installation and upcoming restoration work.  

Saturday, August 25, 2012


DiMeo Brothers has completed the concrete curb & gutter on the north side of Bel-Air Drive. The contractor has been approved for an early start time on Saturday, August 25th starting at 7:00 AM. The contractor will begin installing asphalt surface driveways and backfilling of new curb.

It is anticipated that all driveways will be opened Monday morning, August 27th.

The contractor will begin roadway base work on Monday, August 27th. Temporary ramps at driveways will be provided on Monday and Tuesday. Starting on Wednesday, August 29th, temporary ramps will be removed to completed final grading and preparing of asphaltic paving.

No parking will be allowed in any driveway as the temporary ramps are removed during the day Wednesday through Wednesday night.  Once the paving is completed in front of you home on Thursday, you will be able to access your driveway.

Vehicles are not allowed to be parked along the Bel-Air and Clavey from 7:00 AM to 6:00 PM throughout the week.

Thank you for your patience during the concrete curb & gutter installation and upcoming roadway grading and paving.  

Saturday, August 18, 2012

DiMeo Brothers has completed the concrete curb & gutter on the south side of Bel-Air Drive. The contractor has been approved for an early start time on Saturday, August 18th starting at 7:00 AM. The contractor will begin installing asphalt surface driveways and backfilling of new curb.

It is anticipated that all driveways on the south side of the roadway will be opened Monday morning, August 20th.

Curb preparation and installation work on the north side of Bel-Air and both sides of Clavey Lane will commence on Monday morning, August 20th and weather permitting will be completed by Saturday, August 25th.   Driveway access to these homes will be restored beginning Monday morning, August 27th

All cars parked at residences on the north side of Bel-Air and both sides of Clavey Lane will not have access to driveways after 7:00 AM on Monday morning and should park on Fontana or Pick. No cars should be parked on Bel-Air and Clavey between 7:00 AM and 6:00 PM.  Please plan accordingly. 

Once the concrete curb & gutter is installed, the contractor will begin roadway grading.

The Springman Middle School storm sewer project is completed with the exception of site grading and sod installation.

Thank you for your patience during the concrete curb & gutter work last week and next week.

Monday, August 13, 2012

Just a reminder, curb preparation and installation work on the south side of Bel-Air commenced on Monday morning, August 13th and weather permitting will be completed by Saturday, August 18th.   Driveway access to these homes will be restored beginning Monday morning, August 20th. 
Access from residences to the street will be provided at 2415, 2501 and 2541 Bel Air.  At these locations the orange stringline will be lowered to the ground and pathway will be provided.  When concrete curb is poured there will be a gap left in the curb at these locations for access until the concrete is acceptable to drive on.  These gaps in the curb will be poured during construction of the north side curb.

Friday, August 10, 2012

DiMeo Brothers has completed the underground work for the Bel-Air Drive and Clavey Lane reconstruction project and is working on clean-up and minor contract items.

Curb preparation and installation work on the south side of Bel-Air will commence on Monday morning, August 13th and weather permitting will be completed by Saturday, August 18th.   Driveway access to these homes will be restored beginning Monday morning, August 20th. 

All cars parked at residences on the south side of Bel-Air will not have access to driveways after 7:00 AM on Monday morning and should park on Fontana or Pick. No cars should be parked on Bel-Air and Clavey between 7:00 AM and 6:00 PM.  Please plan accordingly. 

Concrete curb & gutter on the north side of the roadway is schedule for the week of August 20th.

The Springman Middle School storm sewer project was completed last week with site grading and sodding to be completed.

Thank you for your patience during the sewer and water installation portion of the project and upcoming concrete curb & gutter work.

Friday, August 3, 2012



DiMeo Brothers, Inc. installed water services all last week. All water services are now connected to the new water main.

Next week the contractor will connect the new water main to the existing water main. The water main is anticipated to be shut-off for 4-6 hours two days next week. Residents will be notified 24-hours in advance of any water main shut-downs.

The contractor will also perform removal of existing fire hydrants, water valves, and other items; including site clean-up.

Concrete curb & gutter work is scheduled for August 13th on the south side of the roadway.  Residents will be notified prior to concrete work starting. All driveways on the south side of the roadway will be closed during concrete installation and curing.

The Springman Middle School storm sewer project began last week. This work will continue through next week.

Thank you for your patience in advance for the inconvenience of water main shut-downs and upcoming concrete curb & gutter work.