Wednesday, September 26, 2012

Final Asphalt Paving

On Thursday, September 27th, Peter Baker & Sons, Inc. will be on-site to install the final lift of asphalt pavement. The pavement will be cleaned as soon as the sod contractor is completed today. On Thursday morning (tomorrow), the existing asphalt surface will be coated with fresh oil and sand. The oil will help the top coat of asphalt bond to the existing layer. The layer of sand is to help prevent track the oil into your driveways. Please try to keep you driving to a minimum while the oil dries. If you must drive on the oil, please drive slowly to help prevent splattering onto your vehicle.

If paving cannot start Thursday, then it will begin on Friday.

All cars must be removed from the street between 7 AM and 6 PM on the day the roadway will be paved. Parking is available on Fontana or Pick during daytime hours.

Access to driveways will still be available, although there may be short delays during the paving process. Please adjust you schedules accordingly. We will be in contact with the school bus company to notify them of the schedule.

Thanks again for all of your patience during this process.

Friday, September 21, 2012



The landscape sub-contractor was on-site this week grading and installing topsoil in preparation for sod.

Next week the contractor will continue to grade, place topsoil, and install sod throughout the site.

Following the completion of landscape restoration, the final asphalt surface will be installed.

Thank you for your patience during the entire construction season.  

Friday, September 14, 2012

DiMeo Brothers was not on-site during the week.

Landscaping with sod is scheduled to begin next week.

Following the completion of landscape restoration, the final asphalt surface will be installed.

Thank you for your patience during the entire construction season.  We apologize for the delay with landscape restoration.

Friday, September 7, 2012














DiMeo Brothers performed miscellaneous tasks around the site this week including installing chimney seals in manholes, adjusting manhole structures, leak detection testing on water main, testing conductivity of tracer wire along water main, and general site clean-up.

The contractor will begin performing landscape restoration next week.

Following the completion of landscape restoration, the final asphalt surface will be installed.

Thank you for your patience during the entire construction season.